I have witnessed recently that contractors in my area are charging the same amount to put up a seg. wall whether they have to tear out an old one, or it's a new construction site! Do you guys/gals charge a couple of ex $ to tear out and haul, or am I the only one? It seems when contractors "get hungry" that is the first charge "to be waived". Some of the walls we had bid were a couple of dollars a sq. cheaper than us because they hadn't charged for this. W.T.?
__________________
"Improving your piece of the planet"
Reply With Quote
  #2 (permalink)  
Old 05-05-2006, 12:56 AM
sleepy's Avatar
Sapling
 
Join Date: Nov 2005
USDA
Posts: 206
sleepy is an unknown quantity at this point
They "score the blocks?"
Dont look at their prices you will die becoase your overhead is higher. Never match your prices to others. Its your biz your moola and big guys can "eat it"
Reply With Quote
  #3 (permalink)  
Old 05-05-2006, 01:00 AM
Barry's Avatar
Acorn
 
Join Date: Jan 2006
USDA
Posts: 29
Barry is an unknown quantity at this point
No, no. I mean, they tear out an existing wall.............limestone........ties..........an d charge the same sq. ft. price they would charge if there were no wall there to begin with. Has nothing to do with the size of the companies.
__________________
"Improving your piece of the planet"
Reply With Quote
  #4 (permalink)  
Old 05-05-2006, 01:05 AM
Fine Edge's Avatar
Gold Oak Member
 
Join Date: Nov 2005
Location: Monroe, NC
USDA Zone 10
Posts: 680
Fine Edge is an unknown quantity at this point
Doesn't make any sense to me. I'd charge for demo and hauling, but you have to think that grading for the new wall will be minimal now.
Reply With Quote
  #5 (permalink)  
Old 05-05-2006, 01:44 AM
Nebraska's Avatar
Ranger
 
Join Date: Feb 2003
USDA Zone 4
Posts: 1,015
Nebraska is on a distinguished road
welcome to NE.... they all price it at $15-...maybe $19 a SF regardless of what needs to be done.!
Reply With Quote
  #6 (permalink)  
Old 05-05-2006, 07:32 AM
agla's Avatar
Gold Oak Member
 
Join Date: Feb 2003
Location: Cape Cod
USDA Zone 6
Posts: 1,324
agla is on a distinguished road
Are you comparing bids or are you comparing final prices? Bidding specifically what is on the contract and then charging extra for things that are not in a contract has become a very common thing. The contractor writes up the contract to build the wall and makes a subtle reference that all things not specifically in thr quote will be charged for by time and materials. The client tends to miss this and award the bid to the one with the lowest bottom line. After the extras, your bid might have been the lowest.
__________________




Cape Cod Landscape Architect
Reply With Quote
  #7 (permalink)  
Old 05-05-2006, 07:57 AM
Gold Oak Member
 
Join Date: Nov 2004
Location: Long Island, NY
USDA Zone 6
Posts: 1,322
GLAN is an unknown quantity at this point
Quote:
Originally posted by agla
Are you comparing bids or are you comparing final prices? Bidding specifically what is on the contract and then charging extra for things that are not in a contract has become a very common thing. The contractor writes up the contract to build the wall and makes a subtle reference that all things not specifically in thr quote will be charged for by time and materials. The client tends to miss this and award the bid to the one with the lowest bottom line. After the extras, your bid might have been the lowest.

Been seeing and hearing this lately with maintenance estimates/contracts.
Reply With Quote
  #8 (permalink)  
Old 05-05-2006, 10:16 AM
Barry's Avatar
Acorn
 
Join Date: Jan 2006
USDA
Posts: 29
Barry is an unknown quantity at this point
Agla, I understand what it is you are saying. We are comparing bids. Their bid includes tear out, as does ours. And they are ignoring the charges associated with it. We will bid the job, and the homeowners/contractors have told us the "competition" is doing existing wall removal and reinstall for the same sq. ft. price as if it were bare dirt.
__________________
"Improving your piece of the planet"
Reply With Quote
Reply


Thread Tools

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

vB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On



All times are GMT -4. The time now is 07:45 PM.


Powered by vBulletin® Version 3.6.8
Copyright ©2000 - 2008, Jelsoft Enterprises Ltd.
Search Engine Optimization by vBSEO 3.1.0
Copyright ©2003-2007 Ground Trades Xchange, LLC