Hi everybody, I'm new to the biz and have already submitted a few bids, but nothing of this scale.
The total area is around 5 acres, and is mostly flat. It is for a homeowner association. I have a John Deere X500 w/ a 48" deck on it. I think it does about 2.5 Acres/Hour. That is only if the area is fairly straight, as it is not a Zero-turn.
I really need to get this job, I think it would be a good reliable revenue source each week.
I have worked out my hourly rate including overhead and hourly wage. My question is how long do you think I should plan on this job taking for mowing and trimming?
Thanks in advance.