I've been working on this bid and thought of a potential problem. If the sequence of construction is not done in the proper order, it's possible some of the work I've already done could be ripped up for a step that had been forgotten. Is it common to put a clause in the contract to protect against this, so that if work must be done twice I'd be compensated each time? I toured the site again today with the owner and pointed out several items that are required for my work that had been forgotten to this point.
|