The project pack will contain:

A tool checklist - a standard list for the work at hand, and any special tools needed for this project, or special materials, like polymeric sand.

A copy of the contract, including plant types and quantities, hardscape material information, etc - minus any pricing information

Maps to the job site

A copy of the plan

An estimate of the man-hours needed for the job (this is done for incentive program reasons), along with a sheet to track man-hours for the project.

On some projects, if there is something unusual or particularly technical about a project, I'll try to make a sketch or additional notes about how to go about that particular thing.

The planning time I take for this is no more than I take for a project I'd run myself.